Docket Number: | EL07-70-000 |
Region: | New York ISO |
Summary: | This proceeding concerns Hudson Transmission
Partners' complaint against NYISO alleging that NYISO improperly
allowed the Cross Hudson Corporation's (successor to PSEG's
In-City Project) to assume PSEG In-City's place in its Interconnection
Queue, ahead of Hudson Transmission Partners. |
Filings | |
Date | Title |
10-17-2007 |
|
|
Cross
|
10-09-2007 |
|
|
|
08-22-2007 |
|
|
FERC
issued an Order granting Hudson Transmission Partner's June
13, 2007 complaint against NYISO, which alleged that NYISO's interpretation and implementation of the interconnection
queuing provisions of NYISO's Open
Access Transmission Tariff are unjust, unreasonable, and unduly
discriminatory. FERC reasoned that NYISO should have removed
Cross Hudson's Project from the interconnection queue when it
received notice that Cross Hudson was withdrawing the Project.
FERC stated that since the language of the Notice Procedures
were ambiguous, the written withdrawal was sufficient. |
08-17-2007 |
|
|
Hudson
Transmission Partners filed an Answer in response to NYISO's
August 14, 2007 answer. |
08-14-2007 |
|
|
NYISO
filed an Answer in response to the Second Answer of Hudson Transmission
Partners, arguing: (1) Cross Hudson is not a "grandfathered
project" itself and properly remains in NYISO's Interconnection Queue because it has met the requirements
of the NYISO OATT; (2) Cross Hudson has remained in NYISO's interconnection queue because it has satisfied teh requirements of both Attachment S and Attachment X;
and (3) the fact that Cross Hudson has not yet finalized an
Attachment X Interconnection Agreement is irrelevant. |
08-06-2007 |
|
|
Hudson
Transmission Partners filed an Answer in response to Cross Hudson
Corporation's Answer to NYISO's Answer.
HTP argued: (1) the disagreement between NYISO and CHC highlights
the problem of which HTP complained (confusion regarding the
interconnection queue); and (2) CHC is attempting to distance
itself from its only source of legitimacy in that it states
it has transitioned from a pre-Order No. 2003 interconnection
agreement (which it has) to an Attachment X interconnection
agreement (which it does not have). |
07-20-2007 |
|
|
Cross
Hudson Corporation field an Answer in response to NYISO's July 5, 2007 Answer in this proceeding. Cross Hudson
argued that NYISO has applied its Tariff consistently to Cross
Hudson and Cross Hudson has met every milestone in the Tariff
to remain in the interconnection queue, and that NYISO's
clarification is unnecessary and misguided because Cross Hudson
is no more "unique" than other pre-Order No. 2003
projects that during early development did not have access to
the protections now afforded by that Order. |
07-20-2007 |
|
|
Hudson
Transmission Partners filed an opposition to NYISO and Cross
Hudson Corporation's filings in this proceeding. HTP argued:
(1) there are no material facts in dispute; (2) NYISO's
arguments concerning what constitutes written notice are unjust
and unreasonable; (3) NYISO does not present a credible challenge
to the Complaint with regard to FERC precedent; (4) NYISO fails
to explain how Cross Hudson's project is the same "specific
large facility;" (5) NYISO's
unjust and unreasonable practices in maintaining its interconnection
queue must be corrected; and (5) HTP is not anti-competitive
and in-city would not be penalized. |
07-05-2007 |
|
|
Cross
Hudson Corporation filed a motion to intervene in this proceeding.
CHC also filed a protest and motion to dismiss, arguing: (1)
HTP fundamentally misapprehends the purpose of the Interconnection
Queue to establish an order for the performance of studies;
(2) Cross Hudson never exited the Interconnection process; (3)
Cross Hudson should not be removed from the Queue; (4) elimination
of Cross Hudson from the Queue will be destabilizing to the
market; (4) Cross Hudson's project does not cause delay to HTP's
project; and (5) if FERC finds that NYISO violated its Tariff,
the remedy should be directed at NYISO and not Cross Hudson. |
07-05-2007 |
|
|
The
New York Transmission Owners (Central Hudson Gas & Electric,
LIPA, New York State Electric & Gas, Niagara Mohawk Power,
Rochester Gas and Electric) filed a motion to intervene in this
proceeding. |
07-05-2007 |
|
|
NYISO
filed an Answer in response to Hudson Transmission Partners'
June 13, 2007 Complaint in this proceeding. NYISO argued: (1)
Cross Hudson's February 24, 2005 letter to FERC did not constitute
written notice to NYISO of Cross Hudson's withdrawal from the
Interconnection Queue; (2) FERC should not require NYISO to
monitor indirect communications from developers regarding the
status of their projects; (3) HTP has not shown that Cross Hudson
failed to comply with the requirements set forth in the LFIP;
(4) HTP has failed to show that the cancellation of the two-party
Interconnection Agreement required NYISO to remove Cross Hudson
from the Interconnection Queue; (5) HTP has not shown that Cross
Hudson's Queue position was improperly transferred; (6) Cross
Hudson has not requested to change the In-Service date currently
listed in the Interconnection Queue; (7) HTP wrongly characterized
NYISO's position as holding that a
developer need only comply with the requirements of Attachment
S to remain in the Interconnection Queue; and (8) NYISO has
not engaged in undue discrimination against HTP. |
07-03-2007 |
|
|
The
NRG Companies (NRG Power Marketing, Asoria Gas Turbine Power, Arthur Kill Power, Conemaugh Power, Indian River Power, Keystone Power, NRG
Energy Center Dover, NRG Energy Center Paxton, NRG Rockford,
NRG Rockford II, Vienna Power) filed
a motion to intervene in this proceeding. |
07-03-2007 |
|
|
FPL
Energy Generators (FPL Energy Marcus Hook, North Jersey Energy
Associates, Doswell Limited Partnership,
Backbone Mountain Windpower, Mill
Run Windpower, Somerset Windpower,
Meyersdale Windpower, Waymart Wind
Farm, Pennsylvania Windfarms) filed a
motion to intervene in this proceeding. |
07-03-2007 |
|
|
The
PSEG Companies (Public Service Electric and Gas, PSEG Power,
PSEG Energy Resources & Trade) filed a motion to intervene
in this proceeding. |
06-28-2007 |
|
|
The
New York State Public Service Commission filed a notice of intervention
in this proceeding. |
06-14-2007 |
|
|
Hudson
Transmission Partners filed a complaint alleging that NYISO
improperly allowed Cross Hudson Corporation to assume PSEG In-City's
position ahead of HTP in the Interconnection Queue after PSEG
terminated the project. HTP requested that FERC direct NYISO
to remove the PSEG In-City Project from its Interconnection
Queue and place it at the end of the queue. |
06-14-2007 |
|
|
FERC
issued notice of Hudson Transmission Partners' complaint filed
in this proceeding on June 14, 2007. Comments, protests and
motions to intervene must be filed by the deadline. |